1
00:00:00,000 --> 00:00:02,700
Tyler Grace: Based on where I
stand the total job cost to

2
00:00:02,700 --> 00:00:06,360
date, and what I have left and
what extras we have, then I'm

3
00:00:06,360 --> 00:00:10,380
actually going to get this job
done for less than the original

4
00:00:10,380 --> 00:00:18,840
budgeted cost of the project.
Welcome back to another midweek

5
00:00:19,140 --> 00:00:23,540
modern craftsman. I'm looking at
myself right now, and I have on

6
00:00:23,540 --> 00:00:26,300
a winter hat and my harness
sweatshirt, and I feel like I'm

7
00:00:26,300 --> 00:00:29,840
fully bundled up, but maybe my
office is just cold, and it's a

8
00:00:29,840 --> 00:00:35,900
little cold here in New Jersey,
but today I have a really

9
00:00:35,900 --> 00:00:40,540
exciting podcast for all of you,
really, really exciting. It's on

10
00:00:40,540 --> 00:00:43,000
budgeting. Let's talk about
budgeting, because that's the

11
00:00:43,000 --> 00:00:46,780
most exciting topic that I can
think of. No All kidding aside,

12
00:00:46,840 --> 00:00:50,020
I was sitting in my office. It's
my paperwork day. It's Tuesday,

13
00:00:50,020 --> 00:00:54,640
catching up on things, and I'm
getting to the final invoicing

14
00:00:54,640 --> 00:00:57,940
for my porch project that I'm
ratching wrapping up. And I

15
00:00:57,940 --> 00:01:00,600
figured it'd be a good
opportunity to dig into what

16
00:01:00,600 --> 00:01:04,860
that looks like for all of you.
So that's what we're gonna dive

17
00:01:04,860 --> 00:01:08,460
into today, budgeting, what my
budget looks like, how I balance

18
00:01:08,460 --> 00:01:12,540
things out, how I maintain that
budget, how I stay on track. I

19
00:01:12,540 --> 00:01:16,980
believe I did this for this job
early on, as far as what my

20
00:01:16,980 --> 00:01:22,580
budget looks like, I figured, as
I'm wrapping things up, how I

21
00:01:22,580 --> 00:01:27,320
structured this. So I think we
all talk about budget and Nick

22
00:01:27,320 --> 00:01:31,160
and I talk about maintaining a
budget and how a budget is a

23
00:01:31,160 --> 00:01:37,700
living, breathing part of our
construction process. But what

24
00:01:37,700 --> 00:01:43,420
does it look like in real life?
So first off, I am TNM, so what

25
00:01:43,420 --> 00:01:45,940
I'm doing is I'm establishing a
budget. I'm doing pre

26
00:01:45,940 --> 00:01:48,940
construction. That's a separate
cost that's not included in the

27
00:01:49,540 --> 00:01:54,160
construction budget. So for this
job, I charged $5,000 for pre

28
00:01:54,160 --> 00:01:58,360
construction, and that was to
bring in the architect. It did

29
00:01:58,360 --> 00:02:01,500
not pay for the architect
service. That was separate. It

30
00:02:01,560 --> 00:02:05,880
dealt with the township getting
a variance, none of the costs of

31
00:02:05,880 --> 00:02:08,760
engineering. We had to get a
survey. All of that separate.

32
00:02:08,760 --> 00:02:13,500
The $5,000 was my consulting fee
for getting this job through

33
00:02:13,500 --> 00:02:18,120
permitting. So it included
bringing getting the survey

34
00:02:18,120 --> 00:02:23,360
done, but not the cost of the
survey. So being the liaison for

35
00:02:23,360 --> 00:02:26,960
that process, hiring the
surveyor, getting that done,

36
00:02:26,960 --> 00:02:30,080
dealing with the township, some
going to the zoning, meeting

37
00:02:30,080 --> 00:02:34,820
with my client, and then working
with the architect to ensure

38
00:02:34,820 --> 00:02:37,760
that what we were designing made
sense for the client, and then

39
00:02:37,760 --> 00:02:42,220
working with the client to
develop scope, budget and make

40
00:02:42,220 --> 00:02:46,120
sure that everything aligned. So
that was a separate cost here.

41
00:02:46,120 --> 00:02:51,700
So my preliminary budget, what I
go through, basically, I took

42
00:02:51,760 --> 00:02:54,520
what this job looked like on
paper, and what we had designed

43
00:02:54,520 --> 00:02:57,460
and what the existing conditions
were, and I started allocating

44
00:02:57,460 --> 00:03:02,520
costs to this whole job. So
everything from I included a

45
00:03:02,520 --> 00:03:06,600
permit fee in there the
engineering and the design was

46
00:03:06,600 --> 00:03:12,300
part of the cost. Cleanup,
temporary bathrooms, concrete

47
00:03:12,300 --> 00:03:15,180
dumpster, general waste,
dumpster protection for the job

48
00:03:15,180 --> 00:03:19,200
site, work, landscaping, crush
concrete for underneath the

49
00:03:19,200 --> 00:03:24,080
porch, excavation, placing the
footings, materials I needed for

50
00:03:24,140 --> 00:03:28,940
the specified spread footings.
We had some drainage, any

51
00:03:28,940 --> 00:03:32,060
equipment rental that I had, my
machine rental, right? So I

52
00:03:32,060 --> 00:03:36,440
charge out to rent, essentially
from my own business, my Kubota

53
00:03:36,440 --> 00:03:42,400
excavator, concrete demolition.
We had flat work concrete. So

54
00:03:42,400 --> 00:03:46,840
that was a subcontractor
removing and reinstalling a

55
00:03:46,900 --> 00:03:50,980
fence in the yard. We have rough
carpentry, rough carpentry

56
00:03:50,980 --> 00:03:56,140
materials, exterior trim, all of
my post wraps, all of my my

57
00:03:56,140 --> 00:04:00,100
specific quantities of PVC,
right? So I listed out one by

58
00:04:00,100 --> 00:04:03,780
four, one by six, one by eight,
one by 12. I have cortex in

59
00:04:03,780 --> 00:04:10,080
there, red hot adhesive for the
PVC, the screen system. Interior

60
00:04:10,080 --> 00:04:13,860
work. Once I installed the new
door, obviously the new door

61
00:04:14,100 --> 00:04:18,720
roofing. We had a roofing sub do
the roof. He did the gutters,

62
00:04:18,720 --> 00:04:22,700
and he did siding on the
existing gables and

63
00:04:24,200 --> 00:04:29,120
Unknown: dormers on the house.
He did the tie in to the

64
00:04:29,120 --> 00:04:35,360
existing roof. We have storm
doors we did on this job. Let's

65
00:04:35,360 --> 00:04:39,860
see labor to install them. We
have all the decking material,

66
00:04:39,920 --> 00:04:44,140
all of the fasteners, the
handrail that we need, the code

67
00:04:44,140 --> 00:04:48,340
required handrail, and then a
budget for electrical so those

68
00:04:48,340 --> 00:04:51,520
are all the things that I
budgeted for on this project,

69
00:04:51,520 --> 00:04:55,240
that I tried to capture some
sort of realistic cost. So those

70
00:04:55,240 --> 00:05:00,720
are all of the costs that we had
going into. Project that we

71
00:05:00,720 --> 00:05:06,360
tried to capture and tried to
basically account for within

72
00:05:06,360 --> 00:05:07,260
this project.

73
00:05:07,260 --> 00:05:13,140
Tyler Grace: So what I did first
is I got the design paid for. I

74
00:05:13,140 --> 00:05:16,860
got the survey paid for
everything up front to get this

75
00:05:16,860 --> 00:05:20,960
job going, just to make sure
that I wasn't bearing the cost

76
00:05:20,960 --> 00:05:23,600
of this project if something
were to happen this for return

77
00:05:23,600 --> 00:05:26,720
client. But still, I do. I do. I
don't alter my process for

78
00:05:27,140 --> 00:05:30,080
different clients. So then, when
I went to start this job, I took

79
00:05:30,080 --> 00:05:34,820
a substantial deposit that if
all things go according to plan

80
00:05:34,820 --> 00:05:40,540
and we remain on budget, I'll
back out my final invoices out

81
00:05:40,540 --> 00:05:43,300
of that, that deposit that was
taken. But the goal with the

82
00:05:43,300 --> 00:05:47,620
deposit is to cover me for my
most exposed period of this job.

83
00:05:47,620 --> 00:05:53,140
So I took a $25,000 deposit to
start the job and for any of my

84
00:05:53,140 --> 00:05:57,700
pay periods. The goal was to to
never be in the red, so to be

85
00:05:57,760 --> 00:06:01,680
able to maintain that money once
I'm two weeks into an invoice.

86
00:06:01,680 --> 00:06:05,160
If I'm if it's three weeks into
an invoice, right, I'm covered

87
00:06:05,220 --> 00:06:11,640
in whole until I get paid again,
and then that $25,000 is

88
00:06:11,640 --> 00:06:16,260
fulfilled again, just to make
sure that I'm protected. So as

89
00:06:16,260 --> 00:06:20,600
this job progressed, what I do
is every day I keep account of

90
00:06:20,600 --> 00:06:24,800
what materials I'm using, of my
own supplies, what materials I'm

91
00:06:24,800 --> 00:06:28,280
buying, and what labor I have on
this job, whether it's my labor,

92
00:06:28,280 --> 00:06:31,220
it's subcontracted labor,
whatever that looks like. And I

93
00:06:31,220 --> 00:06:36,800
account for this, and I maintain
this every single day. So I go

94
00:06:36,800 --> 00:06:43,720
through starting at the end of
September, 22 and I bought a

95
00:06:43,720 --> 00:06:47,560
screen door, I bought post
bases, I bought structural

96
00:06:47,560 --> 00:06:52,180
hardware, and I charge for that,
and I charge a markup on that,

97
00:06:52,180 --> 00:06:54,820
and then right I paid the
balance of the patio door that

98
00:06:54,820 --> 00:06:59,380
same day. So that goes on to my
budget. I purchased structural

99
00:06:59,380 --> 00:07:03,240
lumber that goes on to my
budget, hangers, LP, sheathing

100
00:07:03,240 --> 00:07:09,300
and tape. I had an hour of my
own labor loading my truck up. I

101
00:07:09,300 --> 00:07:13,020
had two hours dropping off
permits, removing the fence,

102
00:07:13,020 --> 00:07:18,360
setting the job up. I had a
permit. Cost. Everything goes

103
00:07:18,360 --> 00:07:22,940
into this. So the day I started,
the actual job was the 24th so I

104
00:07:22,940 --> 00:07:25,040
have anything that went into
that, right? There were six

105
00:07:25,040 --> 00:07:28,700
hours with me on the excavator.
I spent two hours running to the

106
00:07:28,700 --> 00:07:34,160
dump. I had a concrete dump fee,
I had a fuel fee. I had to rent

107
00:07:34,160 --> 00:07:38,540
a breaker. So all of this goes
into my budget, and I'm

108
00:07:38,540 --> 00:07:43,000
accounting for this. So then
when I go to invoice, my first

109
00:07:43,000 --> 00:07:52,600
work invoice was 922 through 10
eight. It was for $26,986.57 and

110
00:07:52,600 --> 00:07:56,920
that was for all of the work
that went in that I put in place

111
00:07:56,920 --> 00:08:03,120
from 922 till 1028 so I I have
$25,000 that I accounted for. I

112
00:08:03,120 --> 00:08:07,800
exhausted all of that, and now I
submit an invoice for basically

113
00:08:07,800 --> 00:08:12,660
$27,000 so now I'm back in the
green, right, and I'm paid, and

114
00:08:12,660 --> 00:08:16,620
I'm not behind on this job. So I
did this throughout the job. And

115
00:08:16,620 --> 00:08:21,500
the way that I maintain budget
while I'm doing this is I'll go

116
00:08:21,500 --> 00:08:24,980
and I'll look at, hey, what did
I account for demolition? And I

117
00:08:24,980 --> 00:08:28,880
noticed on this job that I did
not anticipate there being as

118
00:08:28,880 --> 00:08:32,660
much concrete as we removed,
because there was a lot of

119
00:08:32,660 --> 00:08:36,560
concrete that was buried. So
that affected my excavation

120
00:08:36,560 --> 00:08:40,720
costs, that affected my time
with my excavator. That also

121
00:08:40,720 --> 00:08:43,780
affected how much fill material
we had to bring in, right?

122
00:08:43,780 --> 00:08:48,640
Because we brought an extra six
tons of material out of there,

123
00:08:48,640 --> 00:08:52,000
as far as concrete and brick and
rubble. So I need then to bring

124
00:08:52,000 --> 00:08:56,680
grade up so it affected three or
four different aspects of the

125
00:08:56,680 --> 00:09:00,960
project. So maybe that might
affect the budget for the job.

126
00:09:00,960 --> 00:09:04,740
Maybe it might not, but I make a
note on my budget that these are

127
00:09:04,740 --> 00:09:12,840
all extras, that if the job goes
over, I can capture that cost at

128
00:09:12,840 --> 00:09:15,660
the end of the job, but I don't
necessarily want to invoice that

129
00:09:15,660 --> 00:09:21,800
client for that money at this
point. If it's I don't want to

130
00:09:21,800 --> 00:09:24,620
say that that's a change order
right now, because I may be good

131
00:09:24,620 --> 00:09:28,640
on budget. So I'm going to make
a note on my invoice. I'm going

132
00:09:28,640 --> 00:09:31,760
to tell the client I think that
we're good on all all aspects of

133
00:09:31,760 --> 00:09:36,380
the job, except for we ran into
more concrete than anticipated.

134
00:09:36,380 --> 00:09:39,860
So we have a higher disposal
fee, we have a higher excavation

135
00:09:39,860 --> 00:09:42,880
fee, we have the higher
equipment rental fee for the

136
00:09:42,880 --> 00:09:46,360
time that it took, and then also
we need to bring in more fill so

137
00:09:46,360 --> 00:09:49,660
I just let them know, maybe we
have that accounted for in other

138
00:09:49,660 --> 00:09:52,600
areas of the budget, but right
now, that's the scope that does

139
00:09:52,600 --> 00:09:57,400
not align with the original
scope that we accounted for in

140
00:09:57,400 --> 00:10:01,260
our pre construction budget. So
then. And the next invoice.

141
00:10:01,260 --> 00:10:05,640
Period is from 10 eight till
1024 I have dump fees in there.

142
00:10:05,640 --> 00:10:10,800
I have my labor. I have all of
my material, pressure treated

143
00:10:10,800 --> 00:10:15,120
material. I have my concrete sub
payment, one payment, two in

144
00:10:15,120 --> 00:10:19,620
there. I have an extra where we
had to bring in eight additional

145
00:10:19,620 --> 00:10:24,800
tons of crushed concrete to
bring grade up, because the way

146
00:10:24,800 --> 00:10:29,300
that it where we had to excavate
and where we had to maintain

147
00:10:29,300 --> 00:10:33,740
grade for the new patio, we
needed to bring up grade on one

148
00:10:33,740 --> 00:10:37,820
area of the property that we
didn't realize initially. So

149
00:10:37,820 --> 00:10:41,920
that was an additional $1,800
and that's to a subcontractor,

150
00:10:41,920 --> 00:10:45,100
so I make a note of that. It's
in bold and it's in red, that I

151
00:10:45,100 --> 00:10:50,260
paid an additional $1,800 on top
of our budgeted subcontractor

152
00:10:50,260 --> 00:10:54,460
expense, and why that was so my
client knows. So just right off

153
00:10:54,460 --> 00:10:57,760
the bat, that's an extra because
it's not my labor. It may not be

154
00:10:57,760 --> 00:11:00,780
something I have accounted for
in the budget, and that's just

155
00:11:00,780 --> 00:11:06,180
an extra cost on this job. We
may still remain on budget for

156
00:11:06,180 --> 00:11:12,000
this project when I look at what
the overall cost is, but this is

157
00:11:12,000 --> 00:11:17,100
not something that I can reduce
my scope, or I can create

158
00:11:17,100 --> 00:11:20,240
efficiencies with my business to
account for that. That's money

159
00:11:20,240 --> 00:11:23,240
that's going out of my pocket to
a subcontractor. So right off

160
00:11:23,240 --> 00:11:26,420
the bat, I just want that to be
an extra for my client to know.

161
00:11:26,660 --> 00:11:30,500
And yeah, maybe we can get back
on budget. But just right from

162
00:11:30,500 --> 00:11:33,440
the outset, you have an extra
$1,800 that I'm paying this

163
00:11:33,440 --> 00:11:35,900
subcontractor. Right there's
nothing that I can do about

164
00:11:35,900 --> 00:11:39,020
that. We'll see what happens on
the on the back end of the job.

165
00:11:39,200 --> 00:11:46,300
So invoice two, I am through
rough framing. We're getting

166
00:11:46,300 --> 00:11:50,440
ready for finishes. I have
deposits for all of my decking

167
00:11:50,440 --> 00:11:55,240
material, so now I can start to
verify. What did I budget for

168
00:11:55,240 --> 00:11:59,200
finishes? What did I budget for
concrete? What did I budget for

169
00:11:59,200 --> 00:12:02,940
my rough framing? What did I
budget for? All of my rough

170
00:12:02,940 --> 00:12:06,300
grade? Are we on track? So I'm
looking at my budget, I'm

171
00:12:06,300 --> 00:12:09,720
looking at my labor, I'm looking
at what our materials are, and

172
00:12:09,720 --> 00:12:13,620
I'm understanding where we where
we land. So on this project, I

173
00:12:13,620 --> 00:12:17,700
wound up overestimating in my
budget some of the material

174
00:12:17,700 --> 00:12:20,360
costs that went into this job,
some of the finishes, and it

175
00:12:20,360 --> 00:12:24,680
costs less money. So right now I
know, well, maybe we can squeak

176
00:12:24,680 --> 00:12:28,700
that $1,800 subcontractor extra
into the budget. Maybe we can

177
00:12:28,700 --> 00:12:32,060
squeak the extra concrete that
we disposed of and

178
00:12:33,740 --> 00:12:38,000
Unknown: excavated and removed
and dumped into the budget. So I

179
00:12:38,000 --> 00:12:40,360
just have a general idea of
that. Again, I have a

180
00:12:40,360 --> 00:12:41,560
conversation with the client.

181
00:12:41,560 --> 00:12:47,020
Tyler Grace: Here's what's owed,
$31,000 here's where we stand.

182
00:12:47,080 --> 00:12:49,720
I'm still confident on our
budget, we're right in the

183
00:12:49,720 --> 00:12:53,260
ballpark of where we should be,
some things or more, some things

184
00:12:53,260 --> 00:12:56,680
or less, but I'm feeling as
though we're good at this point.

185
00:12:57,100 --> 00:13:00,300
You know, more than halfway
through the project, as far as

186
00:13:00,300 --> 00:13:03,780
what our budget looks like,
right? Are we on track at this

187
00:13:03,780 --> 00:13:07,140
point? What I did when I
invoiced for invoice two, which

188
00:13:07,140 --> 00:13:10,740
was at the end of October, I
looked at what I was paid to

189
00:13:10,740 --> 00:13:15,660
date, I looked at the work that
was put in place, and I looked

190
00:13:15,660 --> 00:13:19,920
at what remained of my budget,
and then I listed the extras

191
00:13:19,920 --> 00:13:23,420
that I thought were affecting
our budget, or could potentially

192
00:13:23,480 --> 00:13:27,320
affect our budget in the long
run again, allowing my client to

193
00:13:27,320 --> 00:13:31,160
understand this so we had more
concrete than anticipated, we

194
00:13:31,160 --> 00:13:36,140
had more fill, we had more
excavation demo and regrading. I

195
00:13:36,260 --> 00:13:38,780
there was a hose bib that was
leaking on the side of the

196
00:13:38,780 --> 00:13:43,120
house, a minor but I did go and
buy the parts for that. We fixed

197
00:13:43,120 --> 00:13:43,540
that

198
00:13:44,980 --> 00:13:49,000
Unknown: when we demoed part of
the existing property, there's a

199
00:13:49,000 --> 00:13:54,400
really not very well built brick
retaining wall that kind of

200
00:13:54,400 --> 00:13:57,400
crumbled. So that's an extra
that we're going to have to fix

201
00:13:57,400 --> 00:14:01,980
come the springtime. So I made
note of that. There was more

202
00:14:02,340 --> 00:14:06,060
trim work for the PVC that I
anticipated. Maybe I can tweak

203
00:14:06,060 --> 00:14:08,400
that in the budget. Maybe I
can't, but I know that that's

204
00:14:08,400 --> 00:14:12,360
somewhere that I feel I shorted
myself on labor in our cost

205
00:14:12,360 --> 00:14:15,960
estimate, there was an
additional $1,800 for the Mason

206
00:14:15,960 --> 00:14:18,900
and I also had more electrical
scope than we anticipated. We

207
00:14:18,900 --> 00:14:21,200
added some floodlights. We added
more receptacles than

208
00:14:21,200 --> 00:14:24,200
anticipated. So these are just
all things that I'm noting. Hey,

209
00:14:24,200 --> 00:14:28,100
these were more if our budget
ends up running over, I need to

210
00:14:28,100 --> 00:14:31,880
quantify these things and let
the client know this is where we

211
00:14:31,880 --> 00:14:37,100
stand. These few things were
more than anticipated. It may

212
00:14:37,100 --> 00:14:43,480
affect the budget. So as I'm
going through my second invoice

213
00:14:43,480 --> 00:14:46,600
for this project. I'm making
sure that the work that's put in

214
00:14:46,600 --> 00:14:51,220
place, regardless of where all
of those numbers are, that the

215
00:14:51,220 --> 00:14:55,000
overall budget is still
relatively on track. If it's

216
00:14:55,000 --> 00:14:57,340
not, I want to have a
conversation with my client as

217
00:14:57,340 --> 00:15:00,600
to why it isn't, and if it is, I
want to have the. Conversation

218
00:15:00,600 --> 00:15:04,500
as to why it may not on the back
end, or if we've run into

219
00:15:04,500 --> 00:15:07,260
something, how some of those
extras may have to be accounted

220
00:15:07,260 --> 00:15:11,220
for towards the end of the job.
But right now, I'm feeling as

221
00:15:11,220 --> 00:15:13,800
though we're still on track. I
haven't started finishes, and

222
00:15:13,800 --> 00:15:17,100
sometimes things can get funky
with finishes and take a little

223
00:15:17,100 --> 00:15:20,360
bit more time than anticipated,
but I still feel as though the

224
00:15:20,360 --> 00:15:26,420
budget is is relatively accurate
in that the job is trending in

225
00:15:26,420 --> 00:15:29,840
the right direction. So at this
point, I probably have two more

226
00:15:29,840 --> 00:15:33,500
invoices to go on this project,
whether they're two weeks apart,

227
00:15:33,500 --> 00:15:36,320
three weeks apart. I usually
invoice every two weeks. This

228
00:15:36,320 --> 00:15:39,020
one has been spread out because
I had some traveling to do for

229
00:15:39,020 --> 00:15:43,840
work. I wasn't there five days a
week, four days a week, so not

230
00:15:43,840 --> 00:15:47,920
as much work was getting put in
place as anticipated. So I

231
00:15:47,920 --> 00:15:52,120
spread out my budgeting a little
bit more, but again, I make a

232
00:15:52,120 --> 00:15:58,240
note on this as far as what has
been paid to date, how much work

233
00:15:58,240 --> 00:16:03,360
has been put in place, and how
much budget is left after this

234
00:16:03,360 --> 00:16:10,560
invoice. So moving into invoice
three, and what I'm billing for,

235
00:16:10,560 --> 00:16:17,880
which at this point would be,
actually most of November, I

236
00:16:17,880 --> 00:16:23,540
have communicated to my client
everything they paid for, to

237
00:16:23,540 --> 00:16:26,720
date, how much they've paid to
date, what work has been put in

238
00:16:26,720 --> 00:16:31,640
place, and what work may wind up
being an extra cost, what was

239
00:16:31,640 --> 00:16:35,840
trending higher than anticipated
in our budget. So if so, if we

240
00:16:35,840 --> 00:16:40,480
run into something in the last
invoice or pay period, or work

241
00:16:40,480 --> 00:16:45,100
period, or the second to last
pay period, or work period that,

242
00:16:45,100 --> 00:16:48,820
hey, these things had ran
higher. We're going to need to

243
00:16:48,820 --> 00:16:51,700
capture this cost on the back
end. But right now I'm feeling

244
00:16:51,700 --> 00:16:55,540
pretty good. I think that this
customer understands how I work.

245
00:16:55,540 --> 00:16:59,800
They understand that it's TNM,
they understand the quality of

246
00:16:59,800 --> 00:17:02,040
this project and what's getting
done. And we've had the

247
00:17:02,040 --> 00:17:06,780
conversation that, hey, there's
details that me, we may want to

248
00:17:06,960 --> 00:17:10,200
integrate into this project. Are
you good if this is an

249
00:17:10,860 --> 00:17:14,580
additional cost or this is more
than we anticipated? And they

250
00:17:14,580 --> 00:17:17,460
are, so we're going to keep
moving forward with where we

251
00:17:17,520 --> 00:17:22,280
are. I'm on to invoice three,
which will be my second to last

252
00:17:22,280 --> 00:17:25,160
invoice. I know what my last
invoice will be, and that's

253
00:17:25,160 --> 00:17:27,860
going to be in spring, because I
have some stuff like topsoil and

254
00:17:27,860 --> 00:17:30,680
seed, some final grading that
I'm going to wait until it warms

255
00:17:30,680 --> 00:17:33,800
up where we can actually plant
seed, and I just don't want soil

256
00:17:33,800 --> 00:17:40,840
in there and it washes out all
winter. So we are into invoice

257
00:17:40,840 --> 00:17:45,340
three. I have all the labor
spelled out what everything's

258
00:17:45,340 --> 00:17:48,520
allocated to, right? I have
Tyler three hours framing. I

259
00:17:48,520 --> 00:17:51,820
have a porta potty, cost deck,
fasteners, concrete anchors,

260
00:17:52,120 --> 00:17:57,520
flashing tape. I rented a break
for this project. Every single

261
00:17:57,520 --> 00:18:01,320
cost is accounted for. And then
I moved down towards the end of

262
00:18:01,320 --> 00:18:05,400
November, and I started running
into some things that were not I

263
00:18:05,400 --> 00:18:09,240
was not able to anticipate. So
we went to wrap these columns.

264
00:18:09,540 --> 00:18:14,100
We had purchased prefabricated
columns from ASIC. They were

265
00:18:14,100 --> 00:18:17,580
supposed to go around our six by
sixes. So I measured the inside

266
00:18:17,700 --> 00:18:21,860
of these columns. They are five
and 1116 inside, they were

267
00:18:21,860 --> 00:18:24,680
supposed to be five and three
quarters, which I still feel is

268
00:18:24,680 --> 00:18:27,680
tight for a six by six post,
which can range from five and a

269
00:18:27,680 --> 00:18:30,140
quarter to five and three
quarters. And then, if it's not

270
00:18:30,140 --> 00:18:32,960
perfectly straight, you're
wrapping it with half inch ASIC

271
00:18:33,320 --> 00:18:39,320
might be tight. So we ran into
some issues, and I destroyed

272
00:18:39,320 --> 00:18:44,080
three ASIC post wraps, which my
client shouldn't bear that cost

273
00:18:44,080 --> 00:18:47,560
that's on me. I kept trying to
wrap them, but I realized, hey,

274
00:18:47,560 --> 00:18:50,560
we're not going to be able to
use these prefab post wraps. I'm

275
00:18:50,560 --> 00:18:53,560
going to need to buy additional
half inch material. I'm going to

276
00:18:53,560 --> 00:18:56,320
have to miter, fold these and
wrap them by hand. This is a

277
00:18:56,320 --> 00:19:00,360
completely unanticipated cost,
unfortunately, the client will

278
00:19:00,360 --> 00:19:03,060
have to bear. But I still want
to try and maintain budget here.

279
00:19:03,060 --> 00:19:05,580
So I start, I have the
conversation. Hey, the post

280
00:19:05,580 --> 00:19:08,160
wraps that we got aren't going
to work. We're going to have to

281
00:19:08,160 --> 00:19:10,740
build them by hand. I'm going to
have to get more material here.

282
00:19:10,740 --> 00:19:13,320
We're going to have the labor of
fabricating them and installing

283
00:19:13,320 --> 00:19:17,100
them. It'll be an additional
cost. So I in my budget, I have

284
00:19:17,160 --> 00:19:21,800
bold and red materials extra,
the half inch PVC, the

285
00:19:21,800 --> 00:19:26,780
additional glue, the fasteners I
need. I have the labor in there,

286
00:19:27,860 --> 00:19:31,640
and I have this broken out as
far as all the labor that was

287
00:19:31,640 --> 00:19:34,880
put into making these posts. So
that's an additional cost, and I

288
00:19:34,880 --> 00:19:40,160
have all of the cost associated
with them. $920.20 for

289
00:19:40,160 --> 00:19:46,240
materials. $1,000 for labor.
It's all spelled out there, and

290
00:19:46,240 --> 00:19:51,100
it's in my budget. We go down a
little bit further. We ended up

291
00:19:51,820 --> 00:19:55,480
changing the screen system. So
there was the architect had

292
00:19:55,480 --> 00:19:58,180
speced a structural screen on
the bottom, and then a different

293
00:19:58,180 --> 00:20:01,200
screen on top, and we would have
had to put. A lot of framing in

294
00:20:01,500 --> 00:20:04,860
it would have reduced the size
of the openings, and it would

295
00:20:04,860 --> 00:20:07,260
have just really changed the
feel of the porch. And once we

296
00:20:07,260 --> 00:20:09,900
got it all framed and we got a
trend in PVC, we wanted to

297
00:20:09,900 --> 00:20:12,480
preserve as much of that look
and that scale as possible. And

298
00:20:12,480 --> 00:20:14,880
I felt that building all this
out to put screens on the inside

299
00:20:15,120 --> 00:20:17,940
was really going to change the
look of the job. So I got a hold

300
00:20:17,940 --> 00:20:20,300
of client and said, Hey, are you
good if we change the screen

301
00:20:20,300 --> 00:20:22,580
system. Once we change the
screen system, we're going to

302
00:20:22,580 --> 00:20:24,860
need rails in there. We're going
to need guard rails for the

303
00:20:24,860 --> 00:20:27,200
ports. We're going to have to
make guardrails. So I have an

304
00:20:27,200 --> 00:20:29,300
additional cost for the
materials to make the

305
00:20:29,300 --> 00:20:32,480
guardrails. I decided and
elected to make them myself,

306
00:20:32,900 --> 00:20:35,300
purchase the material, fabricate
them, because they're going to

307
00:20:35,300 --> 00:20:38,000
look better. We'll integrate it
into our screen system, and also

308
00:20:38,000 --> 00:20:40,960
it's going to cost less. So I
have the cost of the extra

309
00:20:40,960 --> 00:20:46,240
material and the labor separated
within my budget in bold, in

310
00:20:46,240 --> 00:20:51,580
red, for her to see what that
cost was, something small, but

311
00:20:51,940 --> 00:20:56,500
we went to go touch up all the
interior paint, and ended up

312
00:20:56,500 --> 00:20:59,740
patching some other areas of the
house while we were there, and

313
00:20:59,740 --> 00:21:02,580
the paint that the house had
been painted with. It dried up,

314
00:21:02,580 --> 00:21:05,820
so we had to buy additional
paint. So that's in the extras.

315
00:21:05,820 --> 00:21:11,220
So I get this invoice done, I
have the total job cost to date,

316
00:21:11,640 --> 00:21:15,240
everything up to this point. The
total job cost I can reflect

317
00:21:15,240 --> 00:21:18,300
what that looks like compared to
what our initial budget is.

318
00:21:18,480 --> 00:21:23,480
We're under budget, and I can
look at what's left on my scope

319
00:21:23,480 --> 00:21:26,840
of work to date. So I have
extras that are left to date,

320
00:21:27,440 --> 00:21:31,220
which is bringing in a little
bit more fail. It's actually the

321
00:21:31,220 --> 00:21:33,920
grade of the fence in the
backyard. We want to raise up,

322
00:21:33,920 --> 00:21:37,100
because our patio came up higher
in one area, so we want to

323
00:21:37,100 --> 00:21:39,680
elevate that fence. So we're
gonna have to pull that fence

324
00:21:39,680 --> 00:21:43,960
and lift that up. So that's an
extra and then we also have

325
00:21:43,960 --> 00:21:46,960
things that are just left on the
budget, installing the screen

326
00:21:46,960 --> 00:21:51,580
system. What else is left on
this general cleanup punch list

327
00:21:51,580 --> 00:21:56,260
items? So I look at what all of
my budget is left, and I compare

328
00:21:56,260 --> 00:22:00,780
that to what the job has costed
to date. What's left on the

329
00:22:00,780 --> 00:22:04,500
outstanding deliverables on the
contract. And I can look at

330
00:22:04,500 --> 00:22:07,860
where we are and what we're
trending as far as budget. I

331
00:22:07,860 --> 00:22:11,400
also, at this point, have added
up all my extras to date, and I

332
00:22:11,400 --> 00:22:14,700
look at what the extras look
like. And I can say, here are

333
00:22:14,700 --> 00:22:17,160
extras to date. They're
$11,597.97

334
00:22:21,660 --> 00:22:25,700
I can look at what I think we
have left in extras, what's the

335
00:22:25,700 --> 00:22:28,280
fence going to cost? What's the
extra grade and we're going to

336
00:22:28,280 --> 00:22:33,080
cost so I can say, hey, we're at
$15,000 in extras for this job.

337
00:22:33,500 --> 00:22:37,280
I can look at what the job cost
to date, and then I can say,

338
00:22:37,280 --> 00:22:42,820
hey, we're still on budget.
We're $5,000 over budget. Worst

339
00:22:42,820 --> 00:22:47,560
case, I'm $15,000 over the
anticipated budget because of

340
00:22:47,560 --> 00:22:50,380
these extras. But the rest of
the job and the rest of the

341
00:22:50,380 --> 00:22:54,220
scope is still on track, I
think, based on where I stand,

342
00:22:54,280 --> 00:22:57,760
the total job cost to date, and
what I have left, and what

343
00:22:57,760 --> 00:23:01,860
extras we have that I'm actually
going to get this da job done

344
00:23:01,980 --> 00:23:05,580
for less than the original
budgeted cost of the project,

345
00:23:05,580 --> 00:23:08,640
which is great. We did extra
work that wasn't anticipated,

346
00:23:08,640 --> 00:23:12,540
but we must have recouped enough
cost within there that this job

347
00:23:12,540 --> 00:23:14,820
wound up being right around what
she thought it was going to be

348
00:23:14,820 --> 00:23:17,520
in the first place. Maybe it's
$5,000 more than she

349
00:23:17,520 --> 00:23:23,240
anticipated, but according to
our budget, I did roughly 12 to

350
00:23:23,240 --> 00:23:26,840
$15,000 worth of work that I
didn't anticipate. But there

351
00:23:26,840 --> 00:23:29,900
must have been numbers within
that budget that I had

352
00:23:29,900 --> 00:23:34,040
overestimated initially, that
are coming down under. So the

353
00:23:34,040 --> 00:23:36,500
client pays what the client
pays. She understands at this

354
00:23:36,500 --> 00:23:39,860
point, with one more invoice
cycle left, that will get done

355
00:23:39,860 --> 00:23:43,480
in spring, that the job is on
track, that our budget is on

356
00:23:43,480 --> 00:23:46,420
track, and she understands what
the extras are. She understands

357
00:23:46,420 --> 00:23:49,600
what she's paid to date, right?
So she's paid that extra $25,000

358
00:23:50,800 --> 00:23:56,080
so what I'm invoicing her for
now is actually less than what

359
00:23:56,080 --> 00:24:00,360
she owes me, because I'm backing
out that $25,000 she's already

360
00:24:00,360 --> 00:24:03,780
paid me for that at the first
billing cycle. I know that what

361
00:24:03,780 --> 00:24:06,120
I have left on the job come
springtime is going to be a

362
00:24:06,120 --> 00:24:09,120
small number, so I'm going to
back that out, and I'm going to

363
00:24:09,120 --> 00:24:13,140
have an invoice for what's due
to date, and that's going to be

364
00:24:13,140 --> 00:24:15,840
everything from this past
billing cycle, minus that

365
00:24:15,840 --> 00:24:16,200
$25,000

366
00:24:17,520 --> 00:24:22,160
Tyler Grace: so at that point,
she's giving me a check. I'll

367
00:24:22,220 --> 00:24:24,800
wrap this job up, I'll punch it
out, and I'll come back at

368
00:24:24,800 --> 00:24:28,100
Spring and we'll execute the
rest of the contract, which are

369
00:24:28,100 --> 00:24:31,640
essentially extras at the end of
this job. But that's how I'm

370
00:24:31,640 --> 00:24:34,640
maintaining the budget
throughout this project. And all

371
00:24:34,640 --> 00:24:36,920
of it's done through notes. It's
done through an Excel

372
00:24:36,920 --> 00:24:40,300
spreadsheet, and it's done just
through tracking payments. It's

373
00:24:40,300 --> 00:24:43,060
done through looking at my
initial budget. So I have my

374
00:24:43,060 --> 00:24:46,060
initial budget up top of my
spreadsheet, and then I track my

375
00:24:46,060 --> 00:24:50,200
job cost right under that. So I
can say, Oh, hey, here's what it

376
00:24:50,200 --> 00:24:53,140
took me to frame this job out,
all the labor of everyone

377
00:24:53,140 --> 00:24:56,560
included. I can go up and I can
look at what I anticipated for

378
00:24:56,560 --> 00:24:59,140
labor costs and say, Yeah, we're
right on track, or we're within

379
00:24:59,140 --> 00:25:01,920
a few hours, or maybe. Maybe
we're slightly over. I can look

380
00:25:01,920 --> 00:25:05,400
at all the PVC that I budgeted
for up top right. I have ASIC

381
00:25:05,400 --> 00:25:10,740
post wraps, $3,300.04 by four.
Post wraps, $2,400 one by four

382
00:25:10,740 --> 00:25:15,360
for the lattice, 1600 20. I even
put 50 quantity PVC for the

383
00:25:15,360 --> 00:25:19,500
lattice, made a vertical one by
four. So I have all of these

384
00:25:19,500 --> 00:25:23,240
notes. I have one by 12 PVC. All
this spelled out. I can go down,

385
00:25:23,240 --> 00:25:25,760
I can look at my invoice from
the lumber company and say,

386
00:25:26,240 --> 00:25:30,680
let's see, hey, my PVC costs x
amount. And then I can go up and

387
00:25:30,680 --> 00:25:33,740
say, hey, you know what? That
was $2,000 less than we thought.

388
00:25:34,220 --> 00:25:37,760
So I have $2,000 worth of wiggle
room in this budget to get

389
00:25:37,760 --> 00:25:40,960
things done the way that I need
them done again, T and M. So my

390
00:25:40,960 --> 00:25:44,260
client is paying what the cost
of things are. I'm creating as

391
00:25:44,260 --> 00:25:47,920
realistic of a budget as
possible, from regards to

392
00:25:48,040 --> 00:25:53,680
schedule, budget scope, but it
may not be 100% accurate. It's

393
00:25:53,680 --> 00:25:57,580
my job, throughout the course of
that job, to communicate to the

394
00:25:57,580 --> 00:26:01,500
client how that budget's
trending, where we've gone over

395
00:26:01,740 --> 00:26:06,240
what may cause an increase in
price. But wait, what may not

396
00:26:06,240 --> 00:26:08,460
right? If I go to the client
say, Hey, we're over on this,

397
00:26:08,460 --> 00:26:11,820
we're over on this, we're over
on this, it's $10,000 more,

398
00:26:13,080 --> 00:26:16,620
Unknown: and it winds up not
being $10,000 more, it makes it

399
00:26:16,620 --> 00:26:19,920
look bad on me. So I say, hey,
look, we're trending at $10,000

400
00:26:20,640 --> 00:26:24,980
more on this job, I felt that I
may have over budgeted the

401
00:26:24,980 --> 00:26:28,400
beginning or the end part the
finishes of this job, right?

402
00:26:28,400 --> 00:26:31,880
That I may have accounted for
extra PVC. I may have accounted

403
00:26:31,880 --> 00:26:35,120
for extra time. So I'm going to
say, hey, we're trending that

404
00:26:35,120 --> 00:26:38,840
we've spent there's some tasks
that have been longer or more

405
00:26:38,840 --> 00:26:42,700
than we anticipated. Maybe it's,
it's to the tune of $10,000 but

406
00:26:42,700 --> 00:26:46,120
I think that we have space in
the budget. So I can look at my

407
00:26:46,120 --> 00:26:49,900
budget, and I have a feeling of
where we're trending. I have a

408
00:26:49,900 --> 00:26:53,080
feeling on a project of this
scale, where I have wiggle room,

409
00:26:53,080 --> 00:26:56,140
where things can be made up,
where I can spend a little bit

410
00:26:56,140 --> 00:26:59,620
more time. And I understood
right after my second invoice, I

411
00:26:59,620 --> 00:27:03,840
understood what had been put in
place, how much work was left

412
00:27:04,140 --> 00:27:07,680
and how much budget was left.
And I understood that I needed

413
00:27:07,680 --> 00:27:11,220
to hustle some I knew that there
was a lot of work that had left

414
00:27:11,220 --> 00:27:14,820
to be done, and that I had to be
very efficient, that I had to

415
00:27:14,820 --> 00:27:20,040
watch how much I was I was how
many hours I was accruing on

416
00:27:20,040 --> 00:27:24,380
this project and what I was
spending. I knew that as I as I

417
00:27:24,980 --> 00:27:29,120
went into the second half of
this job, that my budget was

418
00:27:29,120 --> 00:27:31,400
close. I knew that there were
some things that we ran into

419
00:27:31,400 --> 00:27:34,220
that took a little longer and
cost a little more than we

420
00:27:34,220 --> 00:27:37,400
anticipated. So I knew on the
back half of the job that I had

421
00:27:37,400 --> 00:27:41,500
to I had to be more prudent. I
had to be diligent in how I was

422
00:27:41,500 --> 00:27:44,920
managing this job, on what we
were paying for, on managing my

423
00:27:44,920 --> 00:27:47,740
subs, on making sure that we
weren't overpaying, that we were

424
00:27:47,740 --> 00:27:50,500
getting the scope that we
delivered, and that if we made

425
00:27:50,500 --> 00:27:53,680
changes, how they were going to
impact the budget, and properly

426
00:27:53,680 --> 00:27:58,180
communicating that to my client,
everything has gone pretty much

427
00:27:58,180 --> 00:28:01,260
according to plan. I understood
how it was going to I understood

428
00:28:01,260 --> 00:28:03,480
how the job was trending.
There's some things towards the

429
00:28:03,480 --> 00:28:06,060
end of the job that wound up
being extras that might cost a

430
00:28:06,060 --> 00:28:09,180
little bit more, but they were
communicated to the client. I'm

431
00:28:09,180 --> 00:28:13,440
still aiming to execute this
contract within budget, even

432
00:28:13,440 --> 00:28:17,160
with the extras, because how's
that not a win? I got paid for

433
00:28:17,160 --> 00:28:21,320
all of my time. The client got
everything that they wanted,

434
00:28:21,440 --> 00:28:24,680
plus some possible upgrades and
a better project than they

435
00:28:24,680 --> 00:28:27,800
anticipated, and it's still for
the initial budget that I put in

436
00:28:27,800 --> 00:28:32,240
place. Like, if that's not a
home run, I don't know what is.

437
00:28:32,600 --> 00:28:35,780
So that's how I manage my
budgets. That's how I manage my

438
00:28:35,780 --> 00:28:39,080
projects. And again, at the end
of this, when I send this

439
00:28:39,080 --> 00:28:42,880
invoice out, and I have one more
billing cycle, I'll know, and

440
00:28:43,300 --> 00:28:47,620
the client will know the total
job cost as of today, right? I

441
00:28:47,620 --> 00:28:52,000
have that number to the penny to
the 17 cents on top of the

442
00:28:52,000 --> 00:28:56,680
number. I have all the extras. I
have the anticipated extras. I

443
00:28:56,680 --> 00:29:01,080
have paid the date, and I have
what's due to date so they are

444
00:29:01,080 --> 00:29:04,080
fully aware of everything that's
gone into this job. They

445
00:29:04,080 --> 00:29:06,600
understand all the extras, they
understand every cost that's

446
00:29:06,600 --> 00:29:08,880
gone into it, and they
understand how every decision

447
00:29:08,880 --> 00:29:12,000
that we've made has impacted
that cost. So I'm good to close

448
00:29:12,000 --> 00:29:16,020
this job out till spring, and we
have a general idea of what the

449
00:29:16,020 --> 00:29:20,720
balance of this contract will be
come springtime, but I made sure

450
00:29:20,720 --> 00:29:25,040
that I've managed this project
properly. I also this is a

451
00:29:25,040 --> 00:29:28,880
client that I've worked for for
so long as things have gotten a

452
00:29:28,880 --> 00:29:31,580
little hectic, a little
stressful, as as trimming out

453
00:29:31,580 --> 00:29:35,180
this job had taken a little bit
more than anticipated, I

454
00:29:35,180 --> 00:29:38,720
understood it's a really great
client, that I've really enjoyed

455
00:29:38,720 --> 00:29:41,860
this aspect of the job, that
it's a really amazing job, and

456
00:29:41,860 --> 00:29:44,680
I'm getting a lot of good photos
from it, and it's something that

457
00:29:44,680 --> 00:29:47,140
I could get photographed if I
wanted to, and I'll probably

458
00:29:47,140 --> 00:29:50,320
land another job or two that's
similar to this, from this, that

459
00:29:50,320 --> 00:29:54,940
I am absolutely willing to
concede some of my time to this

460
00:29:54,940 --> 00:29:57,700
project if I'm going over
budget, and I feel like, hey,

461
00:29:57,700 --> 00:30:01,380
it's five grand over that. I.
Don't feel like she should pay,

462
00:30:01,620 --> 00:30:06,060
or that she really doesn't want
to pay. I'm more than willing,

463
00:30:06,240 --> 00:30:09,060
understanding all the costs of
this job, to say, You know what,

464
00:30:09,060 --> 00:30:12,300
I'm going to concede that money
because I made the money that I

465
00:30:12,300 --> 00:30:14,700
needed to elsewhere on the job.
I know that there were markups

466
00:30:14,700 --> 00:30:17,700
that made me money I got. I know
that I captured all of my time.

467
00:30:17,940 --> 00:30:20,840
I know that she was a fantastic
customer. I know that that

468
00:30:20,840 --> 00:30:23,900
$5,000 is not going to make or
break me, and I feel like this

469
00:30:23,900 --> 00:30:26,360
is the right thing to do if it
were to come to it. I have the

470
00:30:26,360 --> 00:30:29,120
ability to do that because I
made my money throughout the

471
00:30:29,120 --> 00:30:31,880
job. I didn't get burnt
throughout this entire job. And

472
00:30:31,880 --> 00:30:35,240
then say, Hey, I'm going to
concede $5,000 I made the money

473
00:30:35,240 --> 00:30:35,960
that I needed to

474
00:30:37,340 --> 00:30:38,900
Tyler Grace: everything's all
good on my end.

475
00:30:40,100 --> 00:30:42,947
Unknown: So I manage the job
with that in mind, right? I'm

476
00:30:43,005 --> 00:30:46,434
not going to stress out, and
this last week of time, or two

477
00:30:46,492 --> 00:30:49,921
weeks just do a crappy job or
put pressure on people to get

478
00:30:49,979 --> 00:30:53,408
done. When we've we've spent
this much time, it's not worth

479
00:30:53,466 --> 00:30:56,952
rushing at the end of the job to
say I need to maintain this

480
00:30:57,011 --> 00:31:00,555
budget, and I'm going to throw
everything else out the window

481
00:31:00,614 --> 00:31:04,042
and just slap it up. No, I'd
rather concede a little bit of

482
00:31:04,100 --> 00:31:07,297
my time, if need be, and
continue to knock this job out

483
00:31:07,355 --> 00:31:10,783
of the park. Because I made
money throughout the whole job.

484
00:31:10,842 --> 00:31:14,328
I didn't work for free. I made
all my markups, anything that

485
00:31:14,387 --> 00:31:17,757
was extra, anything that we ran
into, the client, was very

486
00:31:17,815 --> 00:31:21,302
understanding. So life's a two
way street, right? She's been

487
00:31:21,360 --> 00:31:24,673
very fair. She's been very
understanding. I've worked for

488
00:31:24,731 --> 00:31:28,276
her for almost 15 I think it was
before Selby was born, so 13

489
00:31:28,334 --> 00:31:31,530
years, and I'm going to be
appreciative of that. And if

490
00:31:31,588 --> 00:31:35,307
that's a slight concession on my
behalf, I'm more than okay with

491
00:31:35,366 --> 00:31:38,794
that. So that is my project.
That's my budget. That's how I

492
00:31:38,852 --> 00:31:42,397
ran through this. I know last
time I did this, Dave wanted to

493
00:31:42,455 --> 00:31:45,768
show some of the spreadsheet.
I'm not willing to show the

494
00:31:45,826 --> 00:31:49,371
numbers of what this job totals,
just because it's my clients

495
00:31:49,429 --> 00:31:53,090
business and it's it to me, she
didn't sign up for that. If you

496
00:31:53,148 --> 00:31:56,693
have questions about it, yeah,
I'll answer questions offline.

497
00:31:56,751 --> 00:32:00,180
But I would, I could show a
separate spreadsheet if it were

498
00:32:00,238 --> 00:32:03,783
helpful for for you guys and
girls, but for me, I'm not going

499
00:32:03,841 --> 00:32:07,270
to share this spreadsheet with
you, so you're just going to

500
00:32:07,328 --> 00:32:10,931
have to listen to this podcast
and maybe imagine what it looks

501
00:32:10,989 --> 00:32:14,592
like and what the numbers look
like. But that being said, it's

502
00:32:14,650 --> 00:32:18,312
the same as every other one of
my spreadsheets, right? I have I

503
00:32:18,370 --> 00:32:21,450
have line item budget, I have
scope, I have specifics

504
00:32:21,508 --> 00:32:24,995
attributed to every single task,
and I have payments. I have

505
00:32:25,053 --> 00:32:28,481
credits. I have outstanding
payments due, but I'm not going

506
00:32:28,540 --> 00:32:32,143
to show the spreadsheet again.
David asked me if I could share

507
00:32:32,201 --> 00:32:35,164
that. I'm not going to share
that, just for sake of

508
00:32:35,223 --> 00:32:38,768
preserving my clients private
matters. She didn't sign up for

509
00:32:38,826 --> 00:32:42,545
me showing all of the financials
of this project. So I hope that

510
00:32:42,603 --> 00:32:45,974
this helps you guys and girls
understand how I work, how I

511
00:32:46,032 --> 00:32:49,577
manage jobs, how I how I manage
add ons and extras on jobs at

512
00:32:49,635 --> 00:32:53,238
the beginning versus the end of
the job, how I invoice, what I

513
00:32:53,296 --> 00:32:56,550
leave outstanding. All the
information with budgeting. I

514
00:32:56,608 --> 00:33:00,211
know that we talk a lot about
budgeting, that we manage jobs a

515
00:33:00,270 --> 00:33:03,814
certain way, but in real life,
how am I putting that in place

516
00:33:03,873 --> 00:33:07,359
to ensure that my job is is
staying on budget and staying on

517
00:33:07,418 --> 00:33:10,788
task? And if we've run over,
what does that look like, and

518
00:33:10,846 --> 00:33:14,333
how am I addressing that? So
hopefully this helps all of you

519
00:33:14,391 --> 00:33:17,878
have a better understanding of
that. I appreciate it. I will

520
00:33:17,936 --> 00:33:19,680
catch you all on the next one.

