Hey there, welcome everybody out to podcast number

2
00:00:03.910 --> 00:00:05.170
1663.

3
00:00:05.590 --> 00:00:07.650
In this podcast I'm going to talk about

4
00:00:07.650 --> 00:00:10.570
what happens if we're missing the component of

5
00:00:10.570 --> 00:00:14.950
procurement and we are lacking supply chain management.

6
00:00:15.050 --> 00:00:17.190
If you're interested in that, please stay with

7
00:00:17.190 --> 00:00:17.550
us.

8
00:00:18.390 --> 00:00:20.450
Welcome everybody, I hope you're doing well and

9
00:00:20.450 --> 00:00:21.410
staying safe out there.

10
00:00:23.150 --> 00:00:24.370
I'm pretty excited.

11
00:00:24.930 --> 00:00:27.390
I'm on my way to a boot camp

12
00:00:27.390 --> 00:00:28.530
in Florida.

13
00:00:29.090 --> 00:00:31.189
There's 100 people there, can you believe that?

14
00:00:31.250 --> 00:00:32.430
100 people, super cool.

15
00:00:32.790 --> 00:00:34.850
It's going to be the largest one from

16
00:00:34.850 --> 00:00:36.450
a numbers standpoint that we've hosted.

17
00:00:36.910 --> 00:00:38.250
Took me a long time to get ready

18
00:00:38.250 --> 00:00:38.790
for it actually.

19
00:00:38.950 --> 00:00:41.910
We had to buy so much more supplies,

20
00:00:42.550 --> 00:00:44.270
so many more supplies.

21
00:00:45.050 --> 00:00:47.890
Anyway, so very very exciting.

22
00:00:49.190 --> 00:00:51.250
Also an update on the field engineer book,

23
00:00:51.510 --> 00:00:54.490
the field engineering methods manual.

24
00:00:55.050 --> 00:00:58.290
It was complete and then sent that to

25
00:00:58.290 --> 00:01:01.870
Wes Crawford and Brandon Montero and they had

26
00:01:01.870 --> 00:01:02.830
some final comments.

27
00:01:03.010 --> 00:01:05.550
So Kate was moving through that and with

28
00:01:05.550 --> 00:01:07.730
AI getting better and better each day, we

29
00:01:07.730 --> 00:01:08.930
figured we would do an audit.

30
00:01:09.530 --> 00:01:10.830
So Kate's all the way up to chapter

31
00:01:10.830 --> 00:01:12.690
six and it only has 11 chapters.

32
00:01:12.830 --> 00:01:15.770
She's in seven right now and it's going

33
00:01:15.770 --> 00:01:16.030
good.

34
00:01:16.090 --> 00:01:17.510
So hopefully that comes out soon.

35
00:01:17.930 --> 00:01:19.570
Also we're going to have a field engineer

36
00:01:19.570 --> 00:01:22.250
boot camp in December, first week of December.

37
00:01:22.450 --> 00:01:24.670
So I'm going to start advertising for that

38
00:01:24.670 --> 00:01:26.270
here pretty soon as well.

39
00:01:26.410 --> 00:01:27.250
So really excited.

40
00:01:28.070 --> 00:01:30.310
Let's talk about the topic at hand.

41
00:01:30.410 --> 00:01:32.810
What happens if a component is missing?

42
00:01:33.070 --> 00:01:35.290
By the way, one thing I hope to

43
00:01:35.290 --> 00:01:38.830
do with this is to create a, I

44
00:01:38.830 --> 00:01:39.730
don't know if you would call it a

45
00:01:39.730 --> 00:01:45.610
matrix or a point of reference, but basically

46
00:01:45.610 --> 00:01:48.090
the information so that we could create an

47
00:01:48.090 --> 00:01:49.350
online assessment.

48
00:01:49.970 --> 00:01:53.050
Meaning somebody could come on to the website

49
00:01:53.050 --> 00:01:56.170
and say which component, or basically score their

50
00:01:56.170 --> 00:01:59.070
components and we could say a couple of

51
00:01:59.070 --> 00:01:59.310
things.

52
00:01:59.450 --> 00:02:04.550
Number one, what will happen if that pattern

53
00:02:04.550 --> 00:02:06.690
emerges and those components are not in place

54
00:02:06.690 --> 00:02:09.570
and how to fix it and in what

55
00:02:09.570 --> 00:02:10.470
order to fix it.

56
00:02:10.510 --> 00:02:11.710
And I think that would be really cool.

57
00:02:11.810 --> 00:02:13.910
I learned that from Marcus Sheridan to have

58
00:02:13.910 --> 00:02:15.570
something like that right there on the website.

59
00:02:15.790 --> 00:02:17.570
So that's where we're heading with it.

60
00:02:17.650 --> 00:02:22.310
Now procurement, you all know, we procure materials,

61
00:02:23.410 --> 00:02:25.530
certain types of equipment, especially if the project

62
00:02:25.530 --> 00:02:27.710
has to purchase it and information.

63
00:02:28.430 --> 00:02:31.210
And this is all part of the supply

64
00:02:31.210 --> 00:02:33.870
chain and we must manage the supply chain

65
00:02:33.870 --> 00:02:36.370
with the construction project.

66
00:02:37.070 --> 00:02:39.430
Not exactly like they're at the same tack

67
00:02:39.430 --> 00:02:41.190
time or anything like that, but like they're

68
00:02:41.190 --> 00:02:42.470
one production system.

69
00:02:42.650 --> 00:02:44.390
Meaning a lot of times we think, oh

70
00:02:44.390 --> 00:02:46.330
hey, here's the construction schedule.

71
00:02:47.030 --> 00:02:51.590
And then you know, this procurement thing is

72
00:02:51.590 --> 00:02:54.130
some separate distant log that we have.

73
00:02:54.630 --> 00:02:55.870
And that's just not the case.

74
00:02:55.950 --> 00:02:57.590
We cannot afford to look at it like

75
00:02:57.590 --> 00:02:57.770
that.

76
00:02:58.290 --> 00:03:00.910
The supply chain is a part of the

77
00:03:00.910 --> 00:03:04.950
same procurement or production system.

78
00:03:05.450 --> 00:03:08.530
So managing it is absolutely crucial.

79
00:03:08.990 --> 00:03:11.610
And managing it looks like that we have

80
00:03:11.610 --> 00:03:15.290
a procurement log or procurement on the production

81
00:03:15.290 --> 00:03:16.210
plan early on.

82
00:03:16.910 --> 00:03:20.610
And that we start very, very soon with

83
00:03:20.610 --> 00:03:22.950
long-lead procurement, even in design, like right

84
00:03:22.950 --> 00:03:25.030
away, design and pre-construction.

85
00:03:25.570 --> 00:03:28.470
And then we manage it constantly, at least

86
00:03:28.470 --> 00:03:30.170
every week between PM and super.

87
00:03:30.710 --> 00:03:32.850
And we're managing the individual steps.

88
00:03:32.990 --> 00:03:35.710
We've broken it down and we know what

89
00:03:35.710 --> 00:03:37.770
to do to recover the supply chain.

90
00:03:37.970 --> 00:03:38.130
Okay.

91
00:03:38.290 --> 00:03:40.590
So that is what it looks like to

92
00:03:40.590 --> 00:03:40.830
me.

93
00:03:41.050 --> 00:03:44.530
And if you integrate advanced work packaging, which

94
00:03:44.530 --> 00:03:48.470
will package the project all the way at

95
00:03:48.470 --> 00:03:51.670
the beginning of design properly, so that you

96
00:03:51.670 --> 00:03:56.150
can finish the design, buy out and procure

97
00:03:56.150 --> 00:04:00.710
these individual packages in the right order, that

98
00:04:00.710 --> 00:04:02.530
is ideal as well.

99
00:04:02.670 --> 00:04:04.230
So the bottom line is we're trying to

100
00:04:04.230 --> 00:04:09.290
connect everywhere possible, the building of the work

101
00:04:09.290 --> 00:04:12.930
or the assembly of the work with the

102
00:04:12.930 --> 00:04:13.610
supply chain.

103
00:04:13.870 --> 00:04:20.329
So that everything is targeted or basically landing

104
00:04:20.329 --> 00:04:23.030
or arriving at the due date on the

105
00:04:23.030 --> 00:04:23.950
production plan.

106
00:04:24.170 --> 00:04:26.590
And we're not just building once we get

107
00:04:26.590 --> 00:04:28.710
the materials, meaning everything is synchronized to the

108
00:04:28.710 --> 00:04:31.170
project, beginning with the end in mind.

109
00:04:31.270 --> 00:04:31.450
Okay.

110
00:04:31.850 --> 00:04:34.370
If you don't have these systems up and

111
00:04:34.370 --> 00:04:36.250
running, let me go through these one by

112
00:04:36.250 --> 00:04:36.470
one.

113
00:04:36.570 --> 00:04:39.310
If you don't start early, there's a hundred

114
00:04:39.310 --> 00:04:42.590
percent chance that you will have a major

115
00:04:42.590 --> 00:04:43.990
impact in your production plan.

116
00:04:44.330 --> 00:04:47.590
So if you don't start the procurement efforts

117
00:04:47.590 --> 00:04:50.090
in design and pre-construction and talk to

118
00:04:50.090 --> 00:04:54.070
your owner about an early financial release for

119
00:04:54.070 --> 00:04:57.970
these materials or find some arrangement or ask

120
00:04:57.970 --> 00:05:01.190
them to purchase it directly, then you will

121
00:05:01.190 --> 00:05:02.590
have a massive impact.

122
00:05:02.850 --> 00:05:06.410
The other thing is if you don't package,

123
00:05:06.630 --> 00:05:07.530
oh, this is a good one.

124
00:05:07.710 --> 00:05:10.530
If you don't package everything properly, either in

125
00:05:10.530 --> 00:05:12.950
a traditional method or with advanced work packaging,

126
00:05:13.190 --> 00:05:17.130
then you will procure the right materials in

127
00:05:17.130 --> 00:05:19.430
the wrong order, the wrong sequence and at

128
00:05:19.430 --> 00:05:20.290
the wrong times.

129
00:05:20.650 --> 00:05:21.950
Meaning, let me give you an example.

130
00:05:22.490 --> 00:05:27.530
There was a project in downtown Scottsdale where

131
00:05:27.530 --> 00:05:30.290
the, we actually took over for a different

132
00:05:30.290 --> 00:05:33.170
contractor and I looked at it and the

133
00:05:33.170 --> 00:05:36.230
exterior curtain wall was ordered North, East, South,

134
00:05:36.370 --> 00:05:39.670
West, but actually you could finish the building

135
00:05:39.670 --> 00:05:42.270
up to about six weeks earlier.

136
00:05:42.270 --> 00:05:46.450
If you did a different sequence, Northeast, East,

137
00:05:46.870 --> 00:05:52.250
South, West side, South, East side, West side,

138
00:05:52.650 --> 00:05:55.910
Southwest, Southeast, Northwest, North middle.

139
00:05:56.770 --> 00:05:59.210
And that, that was the ideal sequence, but

140
00:05:59.210 --> 00:06:02.070
because early on they didn't package it properly,

141
00:06:02.110 --> 00:06:03.450
they didn't sequence it properly.

142
00:06:03.630 --> 00:06:06.370
They didn't have the supply chain coming on

143
00:06:06.370 --> 00:06:06.650
time.

144
00:06:07.270 --> 00:06:07.830
Okay.

145
00:06:07.950 --> 00:06:10.530
The other thing is if you are not

146
00:06:10.530 --> 00:06:13.370
on time in the right order, let me

147
00:06:13.370 --> 00:06:14.030
clarify that.

148
00:06:14.030 --> 00:06:15.850
The other thing is if you're not meeting

149
00:06:15.850 --> 00:06:18.790
weekly, you will, even if you started early

150
00:06:18.790 --> 00:06:21.750
enough, you will not see problems in the

151
00:06:21.750 --> 00:06:26.410
supply chain as you go and you will

152
00:06:26.410 --> 00:06:28.050
lose track of those problems.

153
00:06:28.410 --> 00:06:30.010
You will find them out late.

154
00:06:30.230 --> 00:06:32.270
And even if you did start early enough,

155
00:06:32.750 --> 00:06:34.350
you won't have the right materials at the

156
00:06:34.350 --> 00:06:34.810
right time.

157
00:06:35.250 --> 00:06:37.510
And the other thing is if you're not

158
00:06:37.510 --> 00:06:40.050
managing this properly with enough time, you're not

159
00:06:40.050 --> 00:06:42.650
going to do submittal reviews properly.

160
00:06:42.850 --> 00:06:44.490
And the architect is going to feel rushed

161
00:06:44.490 --> 00:06:45.270
and they're not rushed.

162
00:06:45.350 --> 00:06:46.810
And they're not going to do submittal reviews

163
00:06:46.810 --> 00:06:48.790
properly, break it out properly.

164
00:06:49.350 --> 00:06:51.330
And you might even, once all of that's

165
00:06:51.330 --> 00:06:53.330
done, have the wrong materials in the first

166
00:06:53.330 --> 00:06:53.650
place.

167
00:06:54.190 --> 00:06:56.990
So this is a really big component.

168
00:06:57.970 --> 00:07:00.050
If we're missing this, we're in big, big

169
00:07:00.050 --> 00:07:00.450
trouble.

170
00:07:01.170 --> 00:07:04.390
And that's why this is probably one of

171
00:07:04.390 --> 00:07:06.130
the, it's this one's right up there with

172
00:07:06.130 --> 00:07:08.610
the team and having a production plan.

173
00:07:09.350 --> 00:07:11.370
Because, you know, I heard a quote one

174
00:07:11.370 --> 00:07:12.570
time, if you can get this stuff here,

175
00:07:12.650 --> 00:07:13.230
we can build it.

176
00:07:13.290 --> 00:07:15.050
And that's, that's fairly, fairly well true.

177
00:07:15.710 --> 00:07:18.870
So if we're missing this bottom line, we

178
00:07:18.870 --> 00:07:21.730
won't have the materials to build the building.

179
00:07:22.030 --> 00:07:23.810
So I hope you've enjoyed this podcast.

180
00:07:23.950 --> 00:07:24.270
On we go.